Update on the work at the Manava Suite Resort Tahiti

Published 12/28/2017
The Manava Suite Resort Tahiti is moving ahead as scheduled, with all progressing according to our original plans.
The reinforcement phase of the two “motu’s”, with the work encompassing the expansion of the deck will be stopped on December 20th, 2017 for the holiday season. Finishing touches will begin January 08th and ongoing through March 27th, 2018.
The new kitchen for the lagoon front restaurant and the roof covering the seating area, will begin January 8th and continue through March 27th, 2018. The new access to the “motu’s” area , the renovation of the current pool bar and the outdoor restrooms will be completed by May 18th, 2018.
The final hand over of the whole project is planned for end of May or early June 2018. All the renovation work will be put on hold during the dates of December 22nd, 2017 and January 07th, 2018 .
Photo : Benoit Rochet & Mathieu Wenisch de RW Architectes